Construction Schedule
Davis Building – Meeting Place – July and August 2012
Temporary Food Court Development Phase 1 May 30th – July 6th
- Demolition of existing walls
- Removal of flooring
- Preparation of space for food service development
- This phase is complete
Temporary Food Court Development Phase 2 July 9th – August 31st
- Installation of Services Required for Temporary Food court
- Scheduled to Open at the end of August 2012
Installation of Self-Serve Tim Hortons Kiosk July 9th – July 24th
- Scheduled to Open: July 25th
Meeting Place Tim Hortons Redevelopment July 25th – August 24th
- Existing Pizza Pizza and Tim Hortons Outlets will close
- New, larger Tim Hortons will be developed in the space previously occupied by Tim Hortons and Pizza Pizza
- New Tim Hortons Scheduled to Open August 24th
Meeting Place Subway Kiosk Development July 26th – August 24th
- Subway Kiosk to be developed at the current site of the Booster Juice /On the Go Kiosk
- Subway Kiosk is scheduled to open August 24th
For a description of the renovated Meeting Place concepts, click here